Tuesday, February 23, 2010

Week 25 Log A

Plans For The Week
  • Materials needed changed: plywood and possibly fiberglassing materials are available at school so  all I need is my skirt material and vinyl cement which I'm waiting for a final bid to complete the 3
  • I can begin construction but I must wait on my partner to decide on a motor that is acceptable because it could change my dimensions

Friday, February 19, 2010

Week 24 Log B

  • Two bids pending: followed up on them today and I had to re-fax them. Should hear back from them by monday.
  • Started Press Release Paper

Wednesday, February 17, 2010

Week 24 Bid Process Log

I have four bids pending that will give me a complete set of three bids per item that I need.

Tuesday, February 16, 2010

Week 24 Log A

Plans for the Week
  • Order building materials

Friday, February 12, 2010

Week 23 Log B

We've had off for the past two days due to inclement weather. So I have done nothing.

Tuesday, February 9, 2010

Week 23 Log A

Plan of the Week
  • Fill and remaining bids

Friday, February 5, 2010

Week 22 Log B

Things Accomplished
  • Companies found, bids need to be written for each